The project was stalled after An Taisce last July appealed a decision by Meath County Council to grant planning for the 48MW data centre for the IDA business park on the outskirts of Drogheda. © PA Archive/PA Images
Share this article

Gordon Deegan

Tech giant, Amazon have been given permission to build a new data centre in Co Meath despite opposition from An Taisce.

It follows An Bord Pleanala granting planning permission for the project after concluding that the proposal by Tunis Properties LLC would not have a significant impact on climate or legally binding national emission targets in relation to greenhouse gases.

Advertisement

The project was stalled after An Taisce last July appealed a decision by Meath County Council to grant planning for the 48MW data centre for the IDA business park on the outskirts of Drogheda.

Amazon already operates a data centre at the business park and Amazon Web Services (AWS) has stated that cumulative demands for three phases of data centre development at the IDA business park will have a maximum demand of 144MW.

AWS state that the 144MW equates to around 473,040 tonnes of CO2 per year.

The appeal submission by John Spain & Associates says this is a worst case scenario, and it will likely decrease as the national fuel mix decreases its carbon intensity as the grid reaches the target 70 per cent renewable mix by 2030.

Advertisement

The new data centre represents the second phase of development at the business park.

CO2 emissions

The appeal board inspector in the case, Barry O'Donnell recommended that planning permission be granted after pointing out that indirect CO2 emissions from electricity to serve the facility do not count towards or affect Ireland’s reduced emissions target and will instead be regulated under the EU Emissions Trading Scheme, which sets EU-wide targets for sectors within the scheme.

An Amazon commissioned report has estimated that Amazon Web Services (AWS) has made a capital spend of €2 billion on its network of data centres here over the past decade.

In their appeal, An Taisce contended that councils and the appeals board are granting permission for data centres on a case-by-case basis without adequately addressing cumulative impacts of energy use.

Advertisement

Figures provided in the appeal state that there are 70 data centres in operation using 900MW and there are a further eight under consideration, expected to use an additional 250MW.

An Taisce stated that growth has been unchecked and data centres now consume 11 per cent of Ireland’s grid-generated electricity and it is projected to grow to 31 per cent by 2027.

They claimed that uninhibited development of data centres is diluting the benefits of renewable energy generation that has taken place in the last 20-30 years.

Planning policy

Existing and planned data centres likely to be built over the next seven years are projected to require 12.5 terawatts of additional power beyond current generation amounts - enough to power 24 million homes.

Advertisement

In response, the Amazon Web Services (AWS) submission stated that it is not a question of there being a disproportionate number of data centres in Ireland.

Mr Spain stated that planning policy supports the delivery of data centres in Ireland and a location such as the subject site is considered an optimal location for these developments.

He contended that if permission were to be withheld for data centres for the reasons outlined in the An Taisce appeal, no large industrial energy development would be able to secure development, thereby stalling economic growth.

He said the appeal failed to acknowledge that Ireland is recognised as a sustainable location for data centre development, in planning policy terms.

With planning permission secured, AWS is now in a position to apply to Eirgrid to secure a connection agreement for the provision of electricity.

Read More

Message submitting... Thank you for waiting.

Want us to email you top stories each lunch time?

Download our Apps
© BreakingNews.ie 2024, developed by Square1 and powered by PublisherPlus.com