Fast-tracked €150m Adare Bypass may not be ready in time for Ryder Cup

ireland
Fast-Tracked €150M Adare Bypass May Not Be Ready In Time For Ryder Cup
Adare Manor is set to host the Ryder Cup in September 2027. Photo: Getty Images
Share this article

Ken Foxe

A €150 million bypass project fast-tracked so that it would be ready ahead of the Ryder Cup in Adare, Co Limerick may not be finished in time for tournament.

In internal documents, the Department of Transport was warned that time was running out for the 7km road to be finished by the time the event takes place in September 2027.

Advertisement

A letter from Transport Infrastructure Ireland (TII) said there was no way the entire bypass scheme could be finished in time for the 2027 Ryder Cup.

However, TII chief executive Peter Walsh said there was a narrow window to partially complete it to help divert traffic from Adare.

His letter said: “This is an ambitious target given the time remaining, and the work required, however not impossible if early approval to proceed is given, funding provided and resources provided.”

Mr Walsh said all state agencies working together would be “essential” if there was any hope of getting the partial bypass built before 2027.

Advertisement

He also warned that risks could “materialise” during the planning and construction phase which would “undermine” delivery of the scheme before the Ryder Cup started.

Traffic management plan

Mr Walsh said the alternative was to put in place an enormous traffic management plan that would have to deal with an extra 17,000 vehicles passing through the town each day of the tournament.

A department submission for Minister for Transport Eamon Ryan detailed the importance of the bypass scheme, stating Adare was dogged by poor air quality, lengthy journey times, and damage to its tourism prospects.

It said having the full road in place prior to the Ryder Cup was unrealistic, but that a partial scheme could be built in time if it was approved.

Advertisement

The submission said: “Transport Infrastructure Ireland believes that while ambitious, it is possible to deliver this if early approval to proceed is given, and funding and resources are provided.”

Mr Ryan was also told that if this first part of the project went ahead, the rest of it would also ultimately need to be built to “align with the planning approvals [already] in place”.

The submission said more than a dozen State agencies would need to work in concert to deliver on the plan, including four government departments, the local authority, and the OPW.

Costs

On funding the scheme, which has since been given an allocation of €150 million, officials said it would be difficult to give an accurate estimate.

Advertisement

Parts of the submission covering costs were redacted in files released under a Freedom of Information requst, but did say land acquisition would be required and that there were significant constraints on the budget for new roads in 2024 and 2025.

It said, if approved, both the department and TII would closely monitor the project to try and ensure it was completed before the Ryder Cup.

Asked about the records, the department said the road project would help remove traffic from Adare and alleviate a major bottleneck on the national road network.

“In addition, this decision creates the possibility of delivering the bypass ahead of the Ryder Cup, which will be held at Adare Manor in September 2027.

“If delivered before the Ryder Cup, the bypass could assist traffic management during this busy period. It is important to point out that there are risks which may materialise during construction which could slow delivery.”

Read More

Message submitting... Thank you for waiting.

Want us to email you top stories each lunch time?

Download our Apps
© BreakingNews.ie 2024, developed by Square1 and powered by PublisherPlus.com