National Children's Hospital may not open until 2025, expert warns

ireland
National Children's Hospital May Not Open Until 2025, Expert Warns
Dr Paul Davis said the National Children’s Hospital was now one of the most expensive buildings in the world. Photo: PA
Share this article

Vivienne Clarke

A public procurement expert has warned that it would be at least 18 months before the first child is admitted to the new National Children’s Hospital.

Dr Paul Davis, assistant professor in Dublin City University, told RTÉ radio’s Today with Claire Byrne show that since there was not a completed design when the project went to tender, the contractor was legally entitled to make claims.

Advertisement

Earlier the Minister for Health, Stephen Donnelly, told Morning Ireland that the board of the hospital was fighting 2,000 claims amounting to over €760 million from the contractor, BAM.

Dr Davis said that under the terms of the contract, BAM is entitled to put claims in. “Given that we didn't have a design in the first place when we actually went out to contract, there were going to be changes to the design. So what we have is €760 million of claims based on the design that wasn't there. So it's understandable that that has escalated over the years.”

Dr Davis pointed out that the original agreement was that additional costs would be covered to 7 per cent above inflation, but that inflation had been in excess of 20 per cent on a number of occasions for the project.

“Because they didn't have the design there for any changes that were being made as they went along, they were actually having to pay for those as well. So it was an open cheque book, unfortunately.”

Advertisement

Prior to Covid and the war in Ukraine, both given as reasons for delays and escalating costs by the Minster, there were already excess claims and the design had come under question in 2019, added Dr Davis.

“The design was already coming under question in 2019, with PriceWaterhouseCoopers talking about the project management of the hospital board and the lack of project management skills and the lack of project management ability.”

One of the most expensive buildings in the world

The National Children’s Hospital was “an outlier” globally in terms of cost and was now one of the most expensive buildings in the world, he said.

“Given it's a hospital, which will be a fairly standard process because many hospitals are built around the world, it's very much an outlier in the way that we project managed it and the way that we've actually gone out to tender for it.

Advertisement

“We literally went into the marketplace without a final design and without a final budget in place. So the outlier being that we handed over a design process to a group of people.”

Dr Davis questioned if it was “politically expedient” that there wasn’t a completion date yet, given that there could be a general election next year.

“There's still a further probably 18 months before we actually see the first child admitted at this stage. Had it been within a couple of months, then we probably would have expected the board to have approved it (a completion date). But given that it probably is not within a couple of months of May next year, nobody really wants to announce the date, I suspect, because there's an election due next year.”

Dr Davis said it had been “glib” for the Minister for Health to say that the hospital was 90 per cent complete. “We need more detail on this. I think it's the responsibility of the board to publish a much more comprehensive plan of when they believe it's going to be finished and more importantly, when are we going to see the first children being treated?”

Read More

Message submitting... Thank you for waiting.

Want us to email you top stories each lunch time?

Download our Apps
© BreakingNews.ie 2024, developed by Square1 and powered by PublisherPlus.com