Japan approves next step for Fukushima plant wastewater release

world
Japan Approves Next Step For Fukushima Plant Wastewater Release
Japan Fukushima TEPCO Ruling, © AP/Press Association Images
Share this article

By Mari Yamaguchi, Associated Press

Japan’s nuclear regulator has approved the latest details of a release of treated radioactive wastewater from the wrecked Fukushima nuclear power plant into the sea next year.

The approval by the Nuclear Regulation Authority will enable the Tokyo Electric Power Company (Tepco) to start building necessary facilities ahead of the discharge. It came two months after a preliminary greenlight and a subsequent public review process.

Advertisement

Tokyo Electric Power Company Holdings submitted the plan in December based on a government decision last year to release the wastewater as a necessary step for the plant’s ongoing decommissioning.

A massive earthquake and tsunami in 2011 destroyed the Fukushima Daiichi plant’s cooling systems, causing triple meltdowns and the release of large amounts of radiation.

Water that was used to cool the three damaged reactor cores, which remain highly radioactive, has since leaked into basements of the reactor buildings but was collected and stored in tanks.


Japan Nuclear Fukushima
Tanks storing water that was treated but is still radioactive after it was used to cool down spent fuel at the Fukushima Daiichi nuclear power plant in Japan (Hiro Komae/AP/PA)

Advertisement

Local fishing communities and neighbouring countries have raised concerns about potential health hazards from the radioactive wastewater, which Tepco and government officials say will be treated to levels far below releasable standards. They maintain the environmental and health impacts will be negligible.

Japan nuclear authority chairman Toyoshi Fuketa told reporters that the release plan had no major technical or safety issues. He said the regulators will ensure approved procedures are strictly followed with transparency.

The government and Tepco say that of more than 60 isotopes selected for treatment, all but one, tritium, will be reduced to meet safety standards.

Advertisement

Scientists say impacts of long-term, low-dose exposure to tritium for the environment and humans are still unknown. Tritium affects humans more when it is consumed in fish, they say.

The contaminated water is being stored in about 1,000 tanks at the damaged plant.

Officials say they must be removed so that facilities can be built for its decommissioning. The tanks are expected to reach their capacity of 1.37 million tons next year.

Tepco said it plans to transport treated and releasable water through a pipeline from the tanks to a coastal facility, where it will be diluted with seawater and then sent through an undersea tunnel with an outlet about half a mile out to minimise the impact on local fishing and the environment.

Advertisement

The government and Tepco still need to gain local consent for building the tunnel and other related facilities. They plan to begin gradually releasing the treated water in spring 2023.

Japan has sought help from the International Atomic Energy Agency to ensure the water release meets international safety standards and reassure local fishing and other communities and neighbouring countries that have opposed the plan.

Experts from the IAEA visited the plant earlier this year and said Japan was taking appropriate steps for the planned discharge.

In a statement on Friday, Tepco pledged to respond sincerely to the IAEA reviews, ensure safety, provide data to the public and strengthen its radiation monitoring.

Advertisement

The company also vowed to do its utmost to explain the water discharge plans and gain the public’s understanding about the decommissioning.

Read More

Message submitting... Thank you for waiting.

Want us to email you top stories each lunch time?

Download our Apps
© BreakingNews.ie 2024, developed by Square1 and powered by PublisherPlus.com